1995-1996

Shopping Complex (N.G.O. Project)

Client: O.C.C.Z.I.M. (12 months)
Value: ZW $ 2 800 000.00
Supervisor: HBN – Simela Architects

1995-1995

Water And Sewer Reticulation (World Bank Project)

Client: Gwanda Town Council (4 months)
Value: ZW $ 1 750 000.00
Supervisor: Town Engineer – Gwanda

1995 -

Student Residences Including Sewer & Water Reticulation & Civil Works (3 storey & Double storey structures)

Client: National University Of Science & Technology
Value: ZW $148 000 000.00
Supervisor: Mwamuka Mercuri Architects

1995 -

Student Residences Including Sewer & Water Reticulation & Civil Works (3 storey & Double storey structures)

Client: National University Of Science & Technology
Value: US $ 3 500 000.00
Supervisor: Mthupa Simela Architects

1993-1994

3 No. Secondary Schools Including trunk sewers, water reticulation and civil works

Client: Ministry of Public Construction and National Housing (18 months)
Value: ZW $ 10 600 000.00
Supervisor: Ministry of Public Construction

1993-1994

Residence

Client: N.K. Ndlovu (3 months)
Value: ZW $ 180 000.00
Supervisor: Mthupha Matiza Architects

1992-1993

Housing Project (23 No x Houses)

Client: National Railways Of Zimbabwe (6 months)
Value: ZW $ 1 900 000.00
Supervisor: Chief Engineer – N.R.Z.

1992-1993

Khami Prison Kitchens Including Trunk Sewer & Water Reticulation

Client: Ministry of Public Construction & National Housing (18 months)
Value: ZW $ 3 500 000.00
Supervisor: Mthupha Matiza Architects

1992-1993

Electrical Substation

Client: Zimbabwe Electricity Supply Authority (3 months)
Value: ZW $ 300 000.00
Supervisor: Chief Engineer – ZESA

1991-1992

2 x No Secondary Schools Including Trunk Sewers & Water Reticulation and Civil Works

Client: Ministry of Public Construction & National Housing (18 months)
Value: ZW $ 3 000 000.00
Supervisor: Ditto

1991-1992

Z.I.T.F. Stand Building

Client: Dairy Marketing Board (4 months)
Value: ZW $ 800 000.00
Supervisor: G. Keppie Structural Engineers

1991-1992

Z.I.T.F. Stand Building

Client: Z.I.M.E.P. (3 months)
Value: ZW $ 120 000.00
Supervisor: Diagraphis Architects